PUBLIC SAFETY TRAINING FACILITY

Facility Improvement DEPARTMENT OF PUBLIC WORKS - BUREAU OF Continuing, Capital Project PM: Project Manager, Bureau of Facilities

Pages 108–109 in Capital Budget · 2 tables · includes narrative

Page 108

PUBLIC SAFETY TRAINING FACILITY

Functional Area: Facility Improvement Project Type: Continuing, Capital Project Responsible Department: DEPARTMENT OF PUBLIC WORKS - BUREAU OF FACILITIES Project Manager: Project Manager, Bureau of Facilities

Capital Improvement Program

Project Description

This project funds design, planning, and construction for a Public Safety Training Facility.

Project Justification

The existing public safety training sites for Police, Fire, and EMS do not support the current training needs for these Bureaus of the Department of Public Safety.

cip_funding Page 0, Table 0 (p. 108 in full PDF)

Shows capital project funding by source and year.

Source2025202620272028202920302031Total 2026-2031
CDBG0
BOND900,000900,0006,200,00020,000,00026,100,00021,375,00015,000,00089,575,000
PAYGO0
OTHER0
TOTAL900,000900,0006,200,00020,000,00026,100,00021,375,00015,000,00089,575,000

Operating Budget Impact

Public Works staff time will be needed to provide design services, smaller-scale construction and trade services, and manage contracts and outside vendors.

Unexpended/Unencumbered Prior Year Funds $900,000

Page 109

PUBLIC SAFETY TRAINING FACILITY

2026 Deliverables and Objectives

Deliverables are tentative and subject to change Location

Figure
Figure for PUBLIC SAFETY TRAINING FACILITY
deliverables Page 1, Table 0 (p. 109 in full PDF)

Lists project objectives, deliverables, and performance measures.

Deliverable/ObjectiveLocationDistrictFundCost
PUBLIC SAFETY TRAINING FACILITY - MASTER PLAN7180 Highland DrDistrict 9BOND900,000