P.J. MCARDLE ROADWAY (TIP)

Engineering and Construction DEPARTMENT OF MOBILITY AND INFRASTRUCTURE New, Capital Project PM: Deputy Director, Mobility & Infrastructure

Pages 62–63 in Capital Budget · 2 tables · includes narrative

Page 62

P.J. MCARDLE ROADWAY (TIP)

Functional Area: Engineering and Construction Project Type: New, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Deputy Director, Mobility & Infrastructure

Capital Improvement Program

Project Description

Reconstruction of the P.J. McArdle Roadway from the Liberty Tunnels to Grandview Avenue.

Project Justification

The project is on the regional Transportation Improvement Plan.

cip_funding Page 0, Table 0 (p. 62 in full PDF)

Shows capital project funding by source and year.

Source2025202620272028202920302031Total 2026-2031
CDBG0
BOND240,000240,000
PAYGO0
OTHER960,000960,000
TOTAL01,200,000000001,200,000

Operating Budget Impact

Staff time will be needed to manage vendor contracts and review plans.

Unexpended/Unencumbered Prior Year Funds $0

Page 63

P.J. MCARDLE ROADWAY (TIP)

2026 Deliverables and Objectives

Deliverables are tentative and subject to change Location

Figure
Figure for P.J. MCARDLE ROADWAY (TIP)
deliverables Page 1, Table 0 (p. 63 in full PDF)

Lists project objectives, deliverables, and performance measures.

Deliverable/ObjectiveLocationDistrictFundCost
P. J. McARDLE ROADWAY - PRELIMINARY ENGINEERINGP. J. McArdle RoadwayDistrict 2BOND240,000
P. J. McARDLE ROADWAY - PRELIMINARY ENGINEERING (TIP)P. J. McArdle RoadwayDistrict 2OTHER960,000