This is the Mayor’s proposed 2027 budget, pending City Council adoption (expected in December). Figures may change before the budget is adopted.

FLOOD CONTROL PROJECTS

Engineering and Construction DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Recurring, Capital Project PM: Chief Engineer, Mobility and Infrastructure

Pages 55–56 in Capital Budget · 2tables · includes narrative

Page 55

FLOOD CONTROL PROJECTS

Functional Area: Engineering and Construction Project Type: Recurring, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Chief Engineer, Mobility and Infrastructure

Capital Improvement Program

Project Description

This project funds work to mitigate flooding issues in various locations throughout the City. The City undertakes some work on its own, and also in cooperation with other authorities or government agencies.

Project Justification

Flooding is a public safety concern. This project addresses some of those safety concerns while promoting shared delivery of stormwater improvements.

cip_funding Page 0, Table 0 (p. 55 in full PDF)

Shows capital project funding by source and year.

Source2026202720282029203020312032Total 2027-2032
CDBG0
BOND480,0001,165,0001,300,0001,500,0001,500,0001,500,0001,500,0008,465,000
PAYGO169,6470
OTHER0
TOTAL649,6471,165,0001,300,0001,500,0001,500,0001,500,0001,500,0008,465,000

Operating Budget Impact

Staff time will be needed to manage vendor contracts and review plans.

Unexpended/Unencumbered Prior Year Funds $4,198,484

Page 56

FLOOD CONTROL PROJECTS

2027 Deliverables and Objectives

Deliverables are tentative and subject to change Location

Figure
Figure for FLOOD CONTROL PROJECTS
deliverables Page 1, Table 0 (p. 56 in full PDF)

Lists project objectives, deliverables, and performance measures.

Deliverable/ObjectiveLocationDistrictFundCost
STEWART AVE - STORMWATER IMPROVEMENTSStewart AveDistrict 4BOND1,165,000