COMPLETE STREETS
Pages 41–42 in Capital Budget · 2tables · includes narrative
COMPLETE STREETS
Functional Area: Engineering and Construction Project Type: Recurring, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Municipal Traffic Engineer, Mobility and Infrastructure
Capital Improvement Program
Project Description
This project includes intersection improvements, green infrastructure, street furnishings, installation of pavement markings, signage, and traffic signals.
Project Justification
Implementation of adopted City Council policy; promote efficient operation of the system; increase person-capacity on the network; and improve safety. A Complete Streets network will increase the mobility options available to residents of Pittsburgh resulting in lower greenhouse gases, more affordable transportation options, healthier residents, and increased revenue for neighborhood businesses.
Shows capital project funding by source and year.
Operating Budget Impact Assets may require different maintenance practices.
Unexpended/Unencumbered Prior Year Funds $8,149,598
COMPLETE STREETS
2027 Deliverables and Objectives
Deliverables are tentative and subject to change Location

Lists project objectives, deliverables, and performance measures.
| Deliverable/Objective | Location | District | Fund | Cost |
|---|---|---|---|---|
| BINGHAM & S 10TH ST - TRAFFIC SIGNAL IMPROVEMENTS | Bingham St & S 10th St | District 3 | BOND | 14,113 |
| BINGHAM & S 10TH ST - TRAFFIC SIGNAL IMPROVEMENTS (GREEN LIGHT-GO) | Bingham St & S 10th St | District 3 | OTHER | 56,452 |
| BLVD OF THE ALLIES STREETSCAPE IMPROVEMENTS - DESIGN | Blvd of the Allies & Grant St | District 6 | BOND | 800,000 |
| BLVD OF THE ALLIES STREETSCAPE IMPROVEMENTS - DESIGN (PENNDOT MULTIMODAL) | Blvd of the Allies & Grant St | District 6 | OTHER | 1,000,000 |
| BROWNSVILLE RD SAFETY IMPROVEMENT - FINAL DESIGN (TIP) | Brownsville Rd | District 4 | OTHER | 560,000 |
| VISION ZERO IMPLEMENTATION | City-Wide | City-Wide | PAYGO | 1,000,000 |
| LARIMER AVE & E LIBERTY BLVD - TRAFFIC SIGNAL IMPROVEMENTS | Larimer Ave & E Liberty Blvd | District 9 | BOND | 24,924 |
| LARIMER AVE & E LIBERTY BLVD - TRAFFIC SIGNAL IMPROVEMENTS (GREEN LIGHT-GO) | Larimer Ave & E Liberty Blvd | District 9 | OTHER | 99,696 |
| E LIBERTY-NEGLEY AVE SAFETY IMPROVEMENTS (TASA) | Penn Ave & N Negley Ave | District 9 | OTHER | 1,500,000 |