BRIDGE UPGRADES
Pages 34–35 in Capital Budget · 2 tables · includes narrative
BRIDGE UPGRADES
Functional Area: Engineering and Construction Project Type: Recurring, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Chief Engineer, Mobility and Infrastructure
Capital Improvement Program
Project Description
Funding for engineering and upgrades to the 143 City of Pittsburgh-owned bridges.
Project Justification
Bridges are a critical component of our City's infrastructure and require significant repairs to prolong their useful lives. Failure to provide preventive maintenance at an adequate level can lead to more substantial required investments at a later date.
Shows capital project funding by source and year.
Operating Budget Impact
Staff time will be needed to manage outside vendors. Preventative repairs represent substantial savings in the cost of operational maintenance.
Unexpended/Unencumbered Prior Year Funds $519,856
BRIDGE UPGRADES
2026 Deliverables and Objectives
Deliverables are tentative and subject to change Location

Lists project objectives, deliverables, and performance measures.
| Deliverable/Objective | Location | District | Fund | Cost |
|---|---|---|---|---|
| BRIDGE UPGRADES | City-Wide | City-Wide | BOND | 1,600,000 |